AGENDA

7:00–7:30Sign-in and Public Review of Display Stations
Please spend about 5 minutes per station at each of the 5 stations (M Street options, Northern gateway, Eastern gateway, Design elements, PEPCO)
7:30–8:00Call to order and introduction
Background: Jack Evans, Ward 2 Councilmember
Overview: Dan Tangherlini, Acting Director, DC Division of Transportation
PEPCO temporary repair status
8:00–8:20Presentation of Options
  1. Reservoir Road Gateway
  2. 28th Street Gateway
  3. Kit of Parts (Surface Treatment)
  4. M Street Options
    • Trees
    • Without trees
    • Widening
8:20–8:30PEPCO/Utilities Permit Proposal
8:30–9:00Community questions and requests
9:00Commission actions on streetscape project and PEPCO permit proposal